Dragon Rojo or The Red Dragon project is located in the northern desert region of Chile near the town of Mejillones. The ongoing Phase Two of the project consists of the expansion of the coal-fired Thermal Electric Power Plant. AT-PAC, to date, has provided over 400 tons of our Ringlock scaffolding equipment to the project, while SalfaCorp has dismantled over 200 tons of our competitor’s scaffolding material that previously erected and on-site at the time of the award of Phase Two to AT-PAC. By switching to AT-PAC, SalfaCorp is now meeting their project timelines and budgets that were already beginning to fall behind in the early stages of this project. Our competitor’s material has now been 100% dismantled, removed, and replaced with our AT-PAC Ringlock scaffolding.

Customer’s Challenges:

  • Improve inventory management of scaffold material and lower costs

AT-PAC Solution:

  • Ringlock Scaffolding System
  • Provide the GSS program to achieve better utilization of the existing on-site rental scaffolding inventory along
  • Identifying upcoming scaffolding requirements

Impact:

  • 25% savings
  • Phase 2 Project expected to complete 1-month early
  • Phase 3 pre-planning moving forward with AT-PAC as the likely supplier